Successful 5 Years Completion of 1st International Project
"80 KLD ETP for L’Oréal Kenya"

  • Article by Mr.Dattatray Khambayat

INTRODUCTION

The L’OREAL is trying to give clean and healthy environment from the Production activities to act in a responsible and environmentally sustainable manner in our business. We are tried to contribute in global effort of the environment and always improving Environmental Management System. This means we must meet all the requirements for the safe discharge of our wastewater effluents and in strict and accordance with all other legal requirements. This wastewater treatment activity is important to the L'OREAL group because in the event of a malfunction or breakdown, to avoid any pollution and any risk of damaging the groups image.

THE TEAM

Complete Design, Engineering done by M/s AQUCARE SOLUTION ENVIRO ENGINEERS. Electro Mechanical Supply has been done from INDIA. Installation, Commissioning & PG Test with operation training successfully completed by ASEE Team at L'Oréal Kenya

 

THE SOLUTION

In 2016 L'Oréal Kenya awarded turnkey 80 KLD ETP project to M/s Aquacare Solution Enviro Engineers. Which is successfully completed within 4 months of time duration in 2017 The plant is running with designed capacity and desired output water quality meeting all local norms for last 5 years. Which is great achievement and reference.

 

DESIGN & ACHIEVED WATER QUALITY

Parameter Unit Raw Effluent Design Treated Water Quality Avg.Achieved Treated Water Quality
Flow m3/day 40 - 50 50 50
pH   5.5 to 7.5 6 to 8.5 7.5
Total Suspended Solids mg/lit. 3000 <20 <~5
COD mg/lit. 8,000 - 22000 <50 <~20
BOD ( 3 days at 27oC ) mg/lit. 1000 - 3000 <30 <~10
Oil & Grease mg/lit. 500 – 1600 <10 <~5

 